Saturday, January 26, 2008

Bricks are FINISHED!!!

Yesterday (Friday) was the last days our brickies worked onsite. After the bricks were delivered, they were straight back to work, and finished the front and window sils yesterday. I drove around in the morning to check out how much was left and I got out quickly and had a chat to the brickie - just to ask when they would be finished, and thank them for doing a fantastic job. We are extremely pleased - considering we were so worried about the bricks being the wrong colours, they have done a TOP job blending them.











We also have the insulation installed, and the wiring all done ready for plaster.



Thursday, January 24, 2008

Still progressing inside

2 new pallets of our bricks were delivered late Tuesday. Bricking re-commenced today... I will post again when the bricks are done (with photo).
Insulation to the external walls and part of the roof was installed yesterday too.

Tuesday, January 22, 2008

All cleaned up...


Ok, take a good long look. Notice anything? Well, make that do you notice anything missing? Yes that's right, we have had a site clean. What's that? Oh yes, and the brickwork on the portico isn't finished. Does anyone see the bricks they are going to use? Anyone?

Ok, enough with the sarcasm. Saturday we drove past at about midday to find 2 guys doing the site clean. We noticed the nice neat pile of empty pallets in the corner of the block but a distinct lack of left over bricks. We had asked "site supervisor" ages ago (just after we started) and we had been instructed that whatever left over bricks would be piled for us and kept - same with the roof tiles. The roof tiles were still there when we arrived so we were able to save them, but the bricks had been dumped into the skip just before we arrived (damn it!). Matt had a chat to one of the guys cleaning up and he said he had been instructed to just clear the lot. He said that normally there are 1 or 2 pallets that don't get opened and they leave them, but all of our pallets had been opened (to blend them properly) which meant that there was only the bottom layer of bricks remaining on each pallet - so they thought they were all to go. We wanted the left over bricks to be able to build a matching letterbox etc, which I mean - it isn't exactly the end of the world - but more worrying is the fact that there is now a total of 10 bricks left to brick the remainder of the portico... Being a Saturday we immediately tried ringing Metricon but no one was available to take our call, so first thing Monday Matt rang and explained that we now had no bricks left to finish the house. They said they would get back to us but we haven't heard as yet (I imagine they are running around trying to figure out what the heck they do!). I guess if worst comes to the worst we will get Metricon to render the front portico for us, but that's a catch 22 cos I don't particularly want render. Maybe we could get stacked stone out of them? I mean, we aren't really stressing cos it isn't our mistake - I just want the bricks they come up with to match otherwise it will be costing them more than we were charged to upgrade to those bricks.

We are guessing the problem lied with the sidelights - if they had been delivered on schedule the brickwork would have been well and truly finished... so someone has obviously ordered the site clean ages ago and forgot to postpone it when the work wasn't done.


Last Friday we met with "site supervisor". He was lovely and very friendly. He was happy to answer all of our questions and show us everything - including the 2 points that didn't pass their QA assessment. Both have now been rectified. He also told us to go through and check all the electrical points as the wires and wall plates were fitted. There was one issue with a double powerpoint in the ensuite to the left of the vanity. Due to the sliding cavity door the point can't go on that wall, so it was either scrap the while powerpoint (leaving one double p.p in the ensuite) or relocate it into the left hand side of the vanity under the bench - which we have opted for. He told us that bricking should have been finished today (which was hard for the brickies as there were no bricks!), the lock up carpenters were going in to fix up ready for plaster later this week. He said depending on which "team" he was allocated for plaster it may take them 5 days, it may take 2 weeks. He said the painters may then take 2 weeks, then flooring and fittings (cupboards, etc) (? goodness knows how long)then 4 weeks of checks and fix ups, then handover. His generous estimation was 12 weeks, but if things can be kept moving we may be in in 8-10 weeks? Wishful thinking I know.

He has said he was happy to meet with us each week if we like as he only lives 10 mins away and can be there at 7.30am if need be (which we might have to do with Matt and me leaving for work at 8am).

Here is my mock up of what it should look like when the top bricks are finally finished:

Now where are those bricks going to come from? ...

Tuesday, January 15, 2008

A front door and more

As of yesterday (14th Jan) everyone was back to work - as far as our house was concerned anyway. We paid a visit on Saturday to see whether anything had been done over the holidays and discovered that the sidelights had been delivered on the 2/1/08 and were laying in the sitting room waiting to be installed.


On arriving there today, we found that the correct sidelights had been delivered (YAY!!) along with the matching front door.




Was it worth it??? If you had have told me that we wold have had to wait 2 months for them I probably would have said "don't worry about them - we'll take the standard..." but they look awesome don't you think? They will be painted "goanna" (bristol) - which is a mid brown.
There have been doors put on the rear of the garage, and the access door to the garage from the house, so we figure a lock up payment is looming. The front door wasn't locked so we had a sneaky peak inside, and found that internal cavity doors (both ends of the butlers' pantry, the ensuite and the back passage) had been installed, presumably ready for plaster?

We also found that the shower bases (that go under the tiles) had been installed, as had the bath in the bathroom.





As you can see on the external pic, the brickies have made their return, and have completed to the left hand side of the front door, with the right hand side and the top of the portico still to be done.

Dare I say (well, it's only my estimate) we could be in in March? For school holidays please? Sooner would also be GREAT!